Public works
Department (Roads)
1.
PWD Annual Plan:
Under
PWD Annual Plan, 2001-02, 11(eleven) nos. of Road Schemes were taken up and
completed with total fund involvement of Rs. 194.09 lakhs.
Total amount spent for completion of the works was Rs. 192.75 lakhs.
The status of the Road Schems during 2001-02 is indicated below:-
|
Sl.
No |
Name of the Scheme/Programme |
Total Fund Involved (Rs. In lakhs) |
Total Expenditure Incurred |
Physical Progress |
|
1 |
NG Mandakata road |
21.49 |
21.20 |
100% |
|
2 |
Dumunichowki Saraighat Ulta.
|
25.00 |
25.00 |
100% |
|
3 |
Rangmahal Changsari road |
21.93 |
21.25 |
100% |
|
4 |
|
10.00 |
10.00 |
100% |
|
5 |
|
10.00 |
10.00 |
100% |
|
6 |
|
10.00 |
10.00 |
100% |
|
7 |
Rajapara Chandubi road |
10.00 |
10.00 |
100% |
|
8 |
|
10.00 |
10.00 |
100% |
|
9 |
|
28.99 |
28.90 |
100% |
|
10 |
|
24.76 |
24.50 |
100% |
|
11 |
|
21.92 |
21.90 |
100% |
|
|
Total |
194.09 |
192.75 |
-- |
Under PWD Annual Plan 2002-2003,
8(eight) nos. of Road Schemes taken up and completed with total fund
involvement of Rs. 179.00 lakhs.
The Status of the Road schemes during
2002-03 in indicated below:-
|
Sl.
No |
Name of the Scheme/Programme |
Total Fund Involved (Rs. in
lakhs) |
Total Expenditure Incurred (Rs. in
lakhs) |
Physical Progress |
|
1 |
|
20.00 |
20.00 |
100% |
|
2 |
|
24.00 |
24.00 |
100% |
|
3 |
|
20.00 |
20.00 |
100% |
|
4 |
|
22.00 |
22.00 |
100% |
|
5 |
|
22.00 |
22.00 |
100% |
|
6 |
|
24.00 |
24.00 |
100% |
|
7 |
Bhetamukh to |
22.00 |
22.00 |
100% |
|
8 |
|
25.00 |
25.00 |
100% |
|
|
Total |
179.00 |
179.00 |
-- |
Under
PWd Annual Plan, 2003-04, 16(sixteen) nos of total Scheme have been taken up with total fund
involvement of Rs. 856.042 lakhs, out of which an
amount of Rs. 746.00 lakhs has been spent. Out of 16 nos of Schemes, works selecting to 11 nos. of Schemes have
been already been completed. Remaining 5 nos. of Schemes are
ongoing under Annual Plan, 2003-04.
The Status of the Schemes during 2003-04 is
indicated below:-
|
Sl.
No |
Name of the Scheme/Programme |
Total Fund Involved (Rs. in
lakhs)) |
Total Expenditure Incurred (Rs. in
lakhs) |
Physical Progress |
|
1 |
|
50.0 |
50.00 |
100% |
|
2 |
|
50.00 |
50.00 |
100% |
|
3 |
|
25.00 |
25.00 |
100% |
|
4 |
|
25.00 |
25.00 |
100% |
|
5 |
Inspection
Benglow at Amingaon |
27.464 |
27.50 |
100% |
|
6 |
Fulung Lenga raod |
18.62 |
18.50 |
100% |
|
7 |
Arjantal Bhomlahati (Bezsupa)
Road |
30.02 |
30.00 |
100% |
|
8 |
|
106.73 |
80.00 |
95% |
|
9 |
|
79.812 |
70.00 |
98% |
|
10 |
|
39.115 |
10.00 |
50% |
|
11 |
North
Guwahati Ferry approach Road |
165.87 |
165.00 |
100% |
|
12 |
|
5.176 |
5.00 |
100% |
|
13 |
n.G. |
107.16 |
100.00 |
100% |
|
14 |
|
50.00 |
50.00 |
100% |
|
15 |
|
26.075 |
15.00 |
90% |
|
16 |
Pakhamela road |
50.00 |
25.00 |
50% |
|
|
Total |
856.042 |
746.00 |
-- |
Under
PWD Annual Plan, 2004-05, 5(five) nos of total Scheme
have been taken up with total fund involvement of Rs. 159.58 lakhs, out of which an amount of Rs. 49.90 lakhs have already been spent. Out of five nos. of Schemes,
one scheme has already been completed.
The
Status of the road Schemes during 2004-05 is indicated below: -
|
Sl.
No |
Name of the Scheme/Programme |
Total Fund Involved (Rs. in
lakhs) |
Total Expenditure Incurred (Rs. in
lakhs) |
Physical Progress |
|
1 |
|
29.00 |
Nil |
60% |
|
2 |
|
30.00 |
Nil
|
50% |
|
3 |
Nagarbera Namasadrapara road |
21.00 |
Nil |
40% |
|
4 |
Batorhat Chimina road |
49.98 |
49.90 |
100% |
|
5 |
Mirza Lowershipment Raod |
29.60 |
Nil |
-- |
|
|
Total |
159.58 |
49.90 |
-- |
Under Central Assistance Scheme for
2002-03 one road sheme, namely,
Under
Under Central Road Fund for 2002003,
one road scheme, namely, PL Rajapara PWD road with
the total fund of Rs. 350.00 lakhs has been taken up
and 90% of the works have been completed with the total expenditure of Rs.
234.00 lakhs.
3. RIDF-IX
for 2004-05
Under RIDE-IX for 2004-05,
construction work of 7 nos. of RCC Bridges have been taken up and the works are
in progress. The bridges have been started on Kendukona-Changsari
Road(two bridges),
4. NLCPR
for 2004-05:
Under NLCPR for 2004-05, construction
works of two nos. of RCC Bridges have been taken up with a total cost of Rs.
224.24 lakhs.
6. MPNA for 2004-05:
Under MPNA for 2004-05, 8(eight) nos.
of roads have been taken up for construction with total fund involvement of Rs.
978.56 lakhs.
*****
Acievements under
PMGSY works in Kamrup district
during last four
years w.e.f. 2001-02
The
Achievements under PMGSY works in Kamrup district are indicated below:-
A)
PMGSY Roads, 2001-02
i) Total sanctioned estimated Amount : Rs. 723.57 lakhs
ii) Up to date expenditure : Rs. 662.23 lakhs
iii)
Total nos. of Packages taken up : 5 nos.
iv) Total nos. of roads taken up : 12 nos.
v)
Total road length covered : 26.575 kms.
vi)
Total no. of CD works completed : i) HPC : 28 nos.
ii) RCC bridge: 1 no.
1.
Package No. AS-1101/2001-02
|
Sl. No. |
Name of
Roads |
Physical
Progress (Percentage) |
|
1 |
|
100% |
|
2 |
|
100% |
|
3 |
Naokata-Suagpur road |
100% |
2. Package No. AS-1102/2001-02
|
Sl. No. |
Name of
Roads |
Physical
Progress (Percentage) |
|
1 |
Dhupartal-Majuli road |
100% |
|
2 |
|
100% |
3 Package No. AS-1103/2001-02
|
Sl. No. |
Name of
Roads |
Physical
Progress (Percentage) |
|
1 |
|
100% |
|
2 |
|
100% |
4
Package No. AS-1104/2001-02
|
Sl. No. |
Name of
Roads |
Physical
Progress (Percentage) |
|
1 |
|
100% |
|
2 |
|
100% |
|
3 |
Similibari - |
100% |
5.
Package No. AS-1105/2001-02
|
Sl. No. |
Name of
Roads |
Physical
Progress (Percentage) |
|
1 |
|
100% |
|
2 |
|
100% |
B)
PMGY Roads, 2002-03 (Fund not provided)
C) PMGSY roads, 2003-04
i) Total sanctioned estimated Amount : Rs. 1696.30 lakhs
ii) Up to date expenditure : Rs. 1086.40 lakhs
iii)
Total nos. of Packages taken up : 7 nos.
iv) Total nos. of roads taken up : 9
nos.
iv) Total road length to be covered : 60.387 kms.
v)
Total no. of CD works completed :
HPC: 107 nos,
RCC bridge: 11nos.
|
Sl.
No. |
Package No. |
Name of Roads |
Physical Progress (Percentage) |
|
(1) |
(2) |
(3) |
(4) |
|
1 |
AS-1106/2003-04 |
Boko Chamaria via alekjari
Road |
78% |
|
2 |
AS-1107/2003-04 |
Gouripur to |
85% |
|
3 |
AS-1108/2003-04 |
|
63% |
|
4 |
AS-1109/2003-04 |
|
92% |
|
5 |
AS-1110/2003-04 |
|
45% |
|
6 |
AS-1111/2003-04 |
i) Kalutali to Goroimari
road |
100% |
|
ii) |
100% |
||
|
7 |
AS-1112/2003-04 |
i) NH-31 to |
95% |
|
ii) Dhopguri to |
50% |
D) PMGSY Roads 2004-05
i) Total sanctioned estimated Amount : Rs. 1702.45 lakhs
ii)Up to date expenditure : 414.00 lakhs
iii)Total nos. of Packages taken up : 8 nos.
iv)Total nos. of roads taken up : 15 nos.
v)
Total road length covered : 51.179 kms.
vi) Total no. of CD works completed : HPC=68 nos, RCC=3nos.
|
Sl.
No. |
Package No. |
Name of Roads |
Physical Progress (Percentage) |
|
(1) |
(2) |
(3) |
(4) |
|
1 |
AS-1113/2004-05 |
i) Jogipara to |
63% |
|
ii) Dakuapara to |
50% |
||
|
2 |
AS-1114/2004-05 |
i) Passomtola to |
42% |
|
ii) Agumi to |
41% |
||
|
3 |
AS-1115/2004-05 |
i) Sualkuchi to |
15% |
|
ii) Hajo to |
Just
Started |
||
|
4 |
AS-1116/2004-05 |
i) Bakrapara to |
45% |
|
ii) Nahira to |
45% |
||
|
5 |
AS-1117/2004-05 |
i) Rani to Garal
Road |
12% |
|
ii) Naukuchi to |
32% |
||
|
6 |
AS-1118/2004-05 |
i) Sualkuchi to |
22% |
|
7 |
AS-1119/2004+-05 |
i) Baihata to Barka
via |
20% |
|
ii) Rangia to Hajo via |
30% |
||
|
8 |
AS-1120/2004-05 |
i) Murara to |
30% |
|
ii) Rangia to |
25% |
PMGSY Roads 2005-06
i)
Estimates submitted for : Rs. 2692.65
Lakhs
ii) Total nos. of Packages
taken up : 12 nos.
iii) Total nos. of roads
taken up : 21 nos.
iv) Total
length to be covered : 71.98 kms.
v) Up to date
position : All DPR
under process of sanction.
N.B. Progress report has been prepared on
the basis of Report Submitted by S.E. PwD (Roads),
Guwahati vide letter No. T/COM/2002/53/pt/1760 dated