PWD Department
(Building)
During 2001-02, 8(eight) nos. of
schemes have been taken up with total fund involvement of Rs. 506.469 lakhs. During the year all the schemes have been completed
and the building have been handed over to the Health
/Department.
The status of the schemes have been indicated as follows: -
|
Sl.
No. |
Name
of the Scheme/Programme |
Total
Fund involvement (Rs.
In lakhs) |
Total
expenditure incurred (Rs. In lakhs) |
Physical
progress |
|
(i) |
(ii) |
(iii) |
(iv) |
(v) |
|
1 |
Construction
of 30 bedded |
220.02 |
220.02 |
100% |
|
2 |
Completion
of half done work of Nagarbera CHC |
91.50 |
91.50 |
100% |
|
3 |
Completion
of 30 bedded Rural Hospital at Sualkuchi |
53.46 |
53.46 |
100% |
|
4 |
Up
gradation of Bamunigaon PHC to CHC at Bongaon |
48.299 |
48.299 |
100% |
|
5 |
Repairing
& Renovation and Completion of half done work including boundary wall of Dadara PHC |
20.60 |
20.60 |
100% |
|
6 |
Repairing
and Renovation of |
22.70 |
22.70 |
100% |
|
7 |
Repairing
and Renovation of |
21.39 |
21.39 |
100% |
|
8 |
Repairing
and Renovation of Bezera CHC with Staff Quarter |
28.50 |
25.00 |
100% |
|
|
Total |
506.469 |
502.969 |
-- |
During 2002-03, 20 (twenty) nos. of schemes have been taken up and
completed with total fund involvement of Rs. 232.66 lakhs
by the PWD (Building) Department.
The details status of the schemes have been indicated as below:-
|
(i) |
(ii) |
(iii) |
(iv) |
(v) |
|
1 |
Upgradation of Bondapara Sub-Centre to PHC at Bondapara |
14.68 |
14.68 |
100% |
|
2 |
Repairing and
Renovation of State Dispensary at Khetri. |
9.40 |
9.40 |
100% |
|
3 |
Repairing
and Renovation of Moloibari PHC with Staff Quarter. |
4.45 |
4.45 |
100% |
|
4 |
Repairing
and Renovation of Nortap PHC with Staff Quarter. |
6.17 |
6.17 |
100% |
|
5 |
Repairing
of Lokhra Sate Dispensary with Staff Quarter. |
8.65 |
8.65 |
100% |
|
6 |
Repairing
and Renovation of Panikhaiti PHC (Main Blidg at Chandrapur) |
1.5 |
1.5 |
100% |
|
7 |
Repairing
& Renovation of |
10.12 |
10.12 |
100% |
|
8 |
Repairing
& Renovation of |
10.87 |
10.87 |
100% |
|
9 |
Repairing
& Renovation of Azara CHC with staff quarter |
5.20 |
5.20 |
100% |
|
10 |
Repairing
& Renovation of Goral PHE with staff quarter |
7.02 |
7.02 |
100% |
|
11 |
Repairing
& Renovation of State Dispensary at Dhopguri
with staff quarter |
9.55 |
9.55 |
100% |
|
12 |
Repairing
& Renovation of State Dispensary at Hahim with
staff quarter |
11.29 |
11.29 |
100% |
|
13 |
Repairing
& Renovation with staff quarter RFNT Central doctors quarter at Nagarbera |
11.77 |
11.77 |
100% |
|
14 |
Repairing
& Renovation with staff quarter of Sontali PHC |
10.51 |
10.51 |
100% |
|
15 |
Strengthening
of Gumi PHC with staff quarter |
11.84 |
11.84 |
100% |
|
16 |
Repairing
& Renovation with staff quarter of Chaygaon CHC
at Chaygaon |
14.68 |
14.68 |
100% |
|
17 |
Strengthening
of Jorshimoli SHC with staff quarter. |
11.73 |
11.73 |
100% |
|
18 |
Repairing
& Renovation and strengthening of Mirza CHC |
13.13 |
13.13 |
100% |
|
19 |
Construction
of Residential Building Gr-III Judicial Magistrate
at Hajo. |
13.51 |
13.51 |
100% |
|
20 |
Construction
of Hajo CHC under PMGY Scheme. |
|
|
|
|
a) Gr-IV quarter |
9.12 |
9.12 |
100% |
|
|
|
b) Gr-III quarter |
14.83 |
14.83 |
100% |
|
|
c) Doctors
quarter |
12.77 |
12.77 |
100% |
|
|
d) |
7.07 |
7.07 |
100% |
|
|
e)
Compound fencing & approach road |
2.80 |
2.80 |
100% |
|
|
Total |
232.66 |
232.66 |
-- |
During 2004-05,
only three nos. of Schemes have been taken up by the PWD(Building)
Department with total fund involvement of Rs. 17.70 lakhs.
Total expenditure incurred during the year was Rs. 12.99 lakhs.
All the Schemes have been completed during the year.
The Status of the
Schemes are indicated below:-
|
(i) |
(ii) |
(iii) |
(iv) |
(v) |
|
1 |
Strengthening
of Sualkuchi CHC (approach road) |
3.98 |
3.20 |
100% |
|
2 |
Renovation
of Main CHC building at Sualkuchi |
9.79 |
9.79 |
100% |
|
3 |
Construction
of Boundary wall around the South West side of Jyoti
Chitraban Flim Society |
3.93 |
Nil |
100% |
|
Total |
17.70 |
12.99 |
-- |
|